Customer required to eliminate load shedding and reduce grid consumption. Phase one was a 3kVA inverter, 3.5kWh backup and a 15kWh/day PV Generator. We achieved 50% grid consumption In phase 2 we expanded the backup with another 3.5kWh, reducing the grid consumption with an additional 10-15% an doubling the backup duration during load-shedding.